Chronology of a Project
Pre-Construction Process
- 10 + Weeks
- Schedule Meeting
- Develop Scope of Project
- Cost Expectations
- Architect
- Partner Architect
- In-House Designer
- Engineering: Site, Septic, Structural
- Hire Professional Representation
- Local Boards: Historic, Conservation, Health, National Seashore, Zoning
- Finalize Plans, Permit Ready
- Secure Financing
- Client Selections: Appliances, Cabinetry, Flooring, Tiles, Fixtures, Windows, Doors, etc.
- Contract: Cost plus or fixed price with Change Orders
- Building Permit Application + Septic Testing
Construction Process
- 2 + Months
- Permit Approved
- Scheduling
- Mobilization
- Site Work: Septic. Footings, Foundations
- Framing
- Sheathing & Nailing inspection
- Windows, Roofing, Siding, Exterior Trim, paint
- Mechanicals:
Plumbing, Electric, Gas Work
- Rough Inspections: Plumbing, Electric, HVAC, Framing
- Insulation
- Insulation Inspection
- Sheetrock / Plaster
- Interior Finishes: Floors, Trim, Doors, Tile, Cabinetry
- Prime, Paintwork
- Hardware, Accessories
- Mechanical Finishes: Plumbing, Electric, HVAC, Appliances
- Glass, Mirrors
- Exterior Decks, Patios
- Punchlist
- Hardscape / Landscape
- Final Inspections: Plumbing, Electric, HVAC, Building
- Certificate of Occupancy
- Certificate of Completion
Costs
Construction Costs on the Lower Cape 2023
- Custom Homes:
$550+ /SF
- Renovations:
$400+ /SF
- Additions:
$450+ / SF
Factors Influencing Costs
- High Efficiency Mechanical Systems
- New Insulation Requirements:
- R21—R25 Walls 19% increase
- R49—R60 Roofs 22% increase
- Material Cost / Availability
- Labor Shortage on Lower Cape
- Septic: Innovative/Alternative Septic Systems
- H.E.R.S. Home Energy Rating System Requirements
- Mechanical Air Exchanging
- Owners Material Choices, Finishes
- Permitting, Design, Engineering
- Unforeseen Conditions